top of page
Hi Ms. Juliya Lokachuk,
It is with great satisfaction and personal gratitude that we thank you for choosing and trusting our brand.
On this page, you will be able to follow the key steps of the production process and track the status of your order. All content is updated weekly.
Should you have any questions, we are always available and happy to assist.
On behalf of our team at Crete Luxury Art Design, we extend our special thanks.
Your Proform Invoice
Stages of production
Ruth Armchair
Production report
Update date: | 6.09.2024
Brass work phase:
> Step 1 | Mold / Joinery Structure; Completed
> Step 2 | Cut brass bars 100mm / 80mm; Completed
> Step 3 | Manual bending of 80 mm bar; Completed
> Step 4 | Manual bending of 100 mm bar; Completed
> Step 5 | Solid tube cutting for seat support and frame; Completed
> Step 6 | Manual welding of the two structures (100 mm + 80 mm); Completed
> Step 7 | Manual welding of tubes to the frame and seat; Completed
> Step 8 | Shape adjustment (bar cutting) rounded at the end; Not started yet
> Step 9 | Manual sanding of excess solder; Completed
> Step 11 | Manual sanding of the entire brass structure; Started
> Step 10 | Welding detail adjustment Not started yet
> Step 12 | Manual polishing of the entire brass structure; Not started yet
> Step 13 | Hand-plating of brass for the back of the chair; Not started yet
> Step 14 | Hand-sanding of brass sheet; Not started yet
> Step 15 | Hand-polishing of brass sheet; Not started yet
Click to see more
Resin work phase:
> Step 16 | Mold for resin seat structure; Completed
> Step 17 | Mold for resin back structure; Completed
> Step 18 | Resin structure brass seat; Started
> Step 19 | Resin structure brass back; Started
Leather upholstery phase:
> Step 20 | Application of foam to the structure; Not started yet
> Step 21 | Application of leather upholstery; Not started yet
Finishing phase:
> Step 22 | Application of high gloss brass varnish; Not started yet
> Step 23 | Application of varnish to brass sheet; Not started yet
Marble structure phase:
> Step 24 | Marble mold production; Completed
> Step 25 | Marble cutting; Not started yet
> Step 26 | Marble gluing; Not started yet
Final assemble phase:
> Step 27 | Adaptation of brass plate on the back; Not started yet
> Step 28 | Fixing the back structure (upholstered) to the brass structure; Not started yet
> Step 29 | Fixing the seat to the brass structure; Not started yet
Packaging:
> Step 30 | Final quality control; Not started yet
> Step 31 | Packaging of the piece; Not started yet
Stages of production
Abu Dhabi Chair
Production report
Update date: | 9.08.2024
Brass work phase:
> Step 1 | Counter molds for casting; Completed
> Step 2 | Casting molds; Completed
> Step 3 | Delivery to the casting supplier; Completed
> Step 4 | Casting execution of the entire structure; Started
> Step 5 | Welding of the seat structure with the safety bar and fixing; Not started yet
> Step 6 | Sanding excess casting material; Not started yet
> Step 7 | Final sanding (5 phases) of the brass structure; Not started yet
> Step 8 | Polishing (3 phases) of the brass structure; Not started yet
> Step 9 | Plating brass back; Not started yet
> Step 10 | Sanding brass back; Not started yet
> Step 11 | Polishing brass back; Not started yet
Click to see more
Resin work phase:
> Step 12 | Mold for resin seat structure; Completed
> Step 13 | Mold for resin back structure; Completed
> Step 14 | Resin structure brass seat; Started
> Step 15 | Resin structure brass back; Started
Leather upholstery phase:
> Step 16 | Application of foam to the structure; Not started yet
> Step 17 | Application of leather upholstery; Not started yet
Finishing phase:
> Step 18 | Application of high gloss brass varnish brass all stucture; Not started yet
> Step 19 | Application of varnish to brass sheet; Not started yet
Final assemble phase:
> Step 20 | Adaptation of brass plate on the back; Not started yet
> Step 21 | Fixing the back structure (upholstered) to the brass structure; Not started yet
> Step 22 | Fixing the seat to the brass structure; Not started yet
Packaging:
> Step 23 | Final quality control; Not started yet
> Step 24 | Packaging of the piece; Not started yet